Project:
North Middlesex Hospital
Client:
Kier
Specification:
Internal Redecorations
Project Duration:
12 months
Value:
£95,000.00

Works consisted of internal redecorations to wards to new Wing and Podium Block along with internal redecorations to areas damaged by water ingress in HIV ward corridor. This work was carried out in a ‘live’ environment so the programme of works was made flexible to minimise disruption and disturbance, taking into account the hospital’s routines.

Project finished 5 weeks early under budget, with the client extremely happy.

Testimonial from Kiers’ Procurement Post Job Assessment Dept – ‘ the flexibility of the programme ultimately resulted in the bettering of the programme, through co-operation and collaboration from all sides ‘.